    How to Measure the ROI of IT Mapping and Application Rationalization

    How to measure the ROI of IT mapping and application rationalization: costs, returns, baselines, a worked fictional example and the pitfalls to avoid.

    Updated on
    9 min read
    F

    Frédéric Le Bris

    CEO & Co-founder

    TL;DR

    • The ROI of IT mapping and application rationalization is (benefits − costs) ÷ costs, measured over two to three years, because the first year carries the mapping effort and the decommissioning work.
    • The main cost is people's time (the architect who builds the map, the owners who check it, the upkeep), not the tool.
    • The returns you can measure are licences and support contracts retired, time saved on impact analysis, audit preparation time, onboarding time and decision lead time. Avoided incidents are real but hard to value: report them separately.
    • Nothing can be measured without a baseline taken before the work starts: write down today's figures, with their source, first.
    • In our fictional 120-application example, year 1 is slightly negative and the two-year ROI is about 67%. That result depends almost entirely on how many applications are actually retired.

    Most guides to the ROI of digital transformation try to put one number on a whole programme of CRM, automation and cloud projects, and few finance directors believe it. This article narrows the question to something you can measure: the ROI of mapping your information system and of the application rationalization that the map makes possible. You will see what it costs, what it returns, how to take a baseline for each line, and a worked example with every figure labelled as fictional.

    What does an IT mapping and rationalization programme actually cost?

    Most of the cost is the time of the people who build and maintain the map; the tool is a small line next to it. List four kinds of cost and value people's time at a loaded internal day rate agreed with finance:

    • Initial mapping effort. An architect or IT manager inventories applications, flows, servers, owners and capabilities. Application owners spend a few hours each checking their records. This is a one-off cost, and usually the largest one.
    • Upkeep. A map that is not kept up to date loses its value within months. Budget a recurring number of days per month for updates after each change, and a quarterly review with owners.
    • Tooling. A spreadsheet costs nothing in licences but a lot in upkeep and errors; a dedicated tool has a subscription. Use the vendor's published price. For UrbaHive, the pricing page lists Free (0 €, 2 users, 25 applications), Starter (29 € excl. VAT per month, 100 applications) and Professional (99 € excl. VAT per month, 200 applications).
    • Rationalization and decommissioning work. Retiring an application costs time: checking dependencies, migrating or archiving data, terminating the contract, removing accounts. The decommissioning checklist lists the steps. Leave this line out and you overstate the ROI.

    What returns can you measure?

    Five returns can be measured with a baseline, a method and an owner; a sixth, avoided incidents, should be reported but rarely turned into euros. The table shows how to measure each one.

    ReturnBaseline to capture before startingHow to measure afterHard or soft
    Licences and support retiredAnnual cost of each application from contracts and invoicesContracts actually terminated, at their end dateHard
    Faster impact analysisHours spent identifying affected applications and owners per change, on a sample of recent changesSame measure on the next sampleHard (time valued at the day rate)
    Audit and questionnaire preparationDays spent assembling the application inventory for the last audit, insurer or customer questionnaireDays spent on the next oneHard
    Onboarding of IT staffTime before a new hire can answer "what depends on this application?" aloneSame question, next hiresSoft
    Decision speedDays from a request (new tool, change, retirement) to a decisionSame measure, same request typesSoft, report in days
    Avoided incidentsIncidents caused by an unknown dependency over the last 12 monthsSame count over the next 12 monthsReport the count, do not value it

    Two of these deserve a comment. Licences retired is usually the largest line, and it belongs as much to rationalization as to the map: the map shows the redundancies, but a decision and a decommissioning project turn them into savings. The IT rationalization guide and the TIME matrix example cover how those decisions are made. Avoided incidents cannot be counted directly, because an incident that did not happen leaves no trace; count incidents caused by an undocumented dependency before and after, and present the change as an indicator, not as money.

    How do you set the baseline before you start?

    You set the baseline by writing down today's figures, with their source and date, before the first application is mapped: afterwards, nobody remembers.

    1. Licences: export the list of application contracts from purchasing or finance, with annual amount and renewal date. It will be incomplete; that is itself a finding.
    2. Impact analysis: take the last ten or so change requests and ask the people who handled them how long it took to find which applications, flows and owners were affected. A rough estimate per change is enough if you collect it the same way afterwards.
    3. Audit preparation: ask whoever filled in the last audit request or customer security questionnaire how many days it took to compile the list of applications, hosting and vendors.
    4. Onboarding: ask the last two or three IT hires how many weeks it took before they could answer dependency questions without help.
    5. Decision lead time: pull the dates of request and decision from your ticketing tool for a few recent cases.
    6. Incidents: tag in the incident log the ones whose root cause includes "we did not know X depended on Y".

    Keep the baseline in a single sheet, with the person who gave each figure, and show it to finance before the project starts.

    How do you calculate the ROI?

    Use the standard formula, ROI = (total benefits − total costs) ÷ total costs, over a period of two to three years, with the same day rate for costs and time savings. Three rules keep the result credible:

    • Count benefits only once they are real. A licence counts as saved when its contract ends, not when the retirement is decided. Many contracts renew annually, so savings often start the following year.
    • Value time savings with care. Hours saved on impact analysis are not cash unless they free a budget; present them as capacity freed, valued at the day rate, and say so.
    • Separate hard and soft benefits. Put licences, impact analysis and audit preparation in the ROI; show onboarding, decision speed and incidents next to it, not inside it.

    The payback period (the month when cumulative benefits exceed cumulative costs) is often easier for an executive committee to read than a percentage. Give both.

    Worked example: a fictional 120-application organisation

    This example is entirely fictional: the organisation, the figures and the day rate are assumptions chosen to show the method, not results observed at a company. The only real figure is the UrbaHive Professional price taken from the pricing page, because 120 applications exceed the Starter quota.

    Assumptions (fictional): a mid-sized company, 120 applications, loaded day rate 600 €, 8-hour day. Initial mapping takes 25 days of an architect plus half a day for each of 40 application owners (45 days in total). Upkeep is 2 days per month, starting in month 4. The rationalization retires 6 applications with 48,000 € of combined annual licence and support costs, effective mid-year 1, at 5 days of work each. Impact analysis drops from 6 to 2 hours per change, over 60 changes per year. Audit preparation drops from 15 to 4 days.

    Line (fictional)Year 1Year 2
    Initial mapping (45 days × 600 €)−27,000 €0 €
    Upkeep (18 days, then 24 days × 600 €)−10,800 €−14,400 €
    Tool: UrbaHive Professional, 99 € × 12−1,188 €−1,188 €
    Decommissioning work (6 × 5 days × 600 €)−18,000 €0 €
    Total costs−56,988 €−15,588 €
    Licences retired (half year, then full year)+24,000 €+48,000 €
    Impact analysis (60 × 4 h = 240 h × 75 €)+18,000 €+18,000 €
    Audit preparation (11 days × 600 €)+6,600 €+6,600 €
    Total hard benefits+48,600 €+72,600 €
    Net−8,388 €+57,012 €

    Over two years, costs are 72,576 € and benefits 121,200 €: ROI = (121,200 − 72,576) ÷ 72,576 ≈ 67%. Payback falls early in year 2, around month 14. Onboarding (say 3 days saved for each of 4 hires, 7,200 € a year) and the incident count are reported next to this, not inside it.

    Read the sensitivity before presenting it: with 3 applications retired instead of 6, the licence line halves, the decommissioning work halves too, and the two-year ROI drops to about 34% (85,200 € of benefits for 63,576 € of costs). With none retired, the time savings alone do not cover the mapping effort within two years. The map pays for itself through the decisions it enables. That is why a rationalization plan, built for instance with a TIME matrix, belongs in the same business case.

    What are the common pitfalls?

    The most common pitfall is claiming savings that were decided but never delivered. The others are close behind:

    • No baseline. Without "before" figures there is no ROI, only an opinion. Take the baseline in week one.
    • Counting the licence, forgetting the exit. Decommissioning costs time, and some contracts carry notice periods or exit fees. Include them.
    • Valuing every saved hour as cash. Freed capacity is real value, but finance will discount it if you present it as savings. Label it.
    • Putting a price on avoided incidents. Any figure is a guess and weakens the rest of the case. Report a count.
    • Letting the map decay. A map that is not maintained stops producing returns within months. The upkeep line is not optional.
    • Attributing everything to the tool. The returns come from the map and the decisions made with it. A tool lowers the cost of building and keeping the map; it does not make the decisions. See the application portfolio management guide for the governance side.

    Where does UrbaHive fit?

    UrbaHive holds the map; it does not calculate ROI or TCO for you. What it provides for the method above:

    • The inventory that the baseline needs: applications, flows, servers, programs, capabilities, processes and people, with a responsible person and additional contacts for each application. See what IT mapping covers.
    • Costs where you want them: UrbaHive has no cost tracking, but custom fields (7 field types on 7 object types, searchable) can carry an annual licence cost, a renewal date or a TIME verdict on each application. The calculation stays in your spreadsheet.
    • Faster impact analysis: from an application, server, process or person, the impact analysis shows direct dependencies (one level) upstream and downstream, on five layers. It does not follow application-to-application flows transitively and has no export.
    • Redundancy signals: the capabilities × applications coverage matrix flags capabilities with no application and those served by more than four.
    • Traceability: the audit log records each change with before and after values; it can be viewed in the app, not exported.

    FAQ

    What is the ROI of an IT mapping tool?

    It is the value of the decisions and time savings the map enables, minus the cost of building and maintaining it, of which the tool is usually the smallest part. The returns come mainly from licences retired after rationalization, faster impact analysis and shorter audit preparation. There is no universal figure: compute it with your own baseline over two to three years.

    How do I calculate the ROI of application rationalization?

    Take the annual licence and support cost of each application you retire, count it from the date the contract actually ends, and subtract the cost of the decommissioning work (dependency checks, data migration or archiving, contract exit). Divide the net result by the total cost, over at least two years, since savings often start after the next renewal date.

    How long before IT mapping pays for itself?

    It depends on how fast the map leads to retirements. In our fictional example, payback comes around month 14, because licence savings start mid-year 1 and the initial mapping effort is front-loaded. If no application is retired, payback relies on time savings alone and takes longer.

    Should avoided incidents be included in the ROI?

    Report them, but keep them out of the figure. An incident that did not happen cannot be priced reliably. Count incidents caused by an undocumented dependency before and after, and present the change next to the ROI.

    Does UrbaHive calculate ROI or TCO?

    No. UrbaHive holds the inventory, the dependencies, the owners and the impact analysis. You can store costs or renewal dates in custom fields on applications, but the ROI calculation stays in your own model.

    What baseline do I need before mapping my information system?

    At minimum: the list of application contracts with annual costs, the time spent on impact analysis for a sample of recent changes, and the days spent preparing the last audit or security questionnaire. Write them down with their source and date before you start.

    Build the business case on a map you can trust

    Start by writing your baseline, then map the scope that carries the most licences. UrbaHive's free plan (2 users, 25 applications, no credit card, no time limit) is enough to try it on that first scope, and you can start in a couple of hours. Create your free UrbaHive account.